1.
|
All Rides
|
Advantage
|
All Components
|
10 yrs Overhaul (every 10 years)
|
Required by the Rides’ Manuals
|
|
2.
|
High
Flyer
|
A. R.
M
|
See
the High Flyer Manual, P. 6.12.
|
Bi-Annual
Dye Penetrant, Magnetic Particle and Ultrasonic (see High-Flyer Manual P.
6.11)
|
High
Flyer Manual Pages 6.10, 6.11 and 6.12
|
|
3.
|
Ali
Baba
aka/1001
Nights
|
A. R.
M.
|
NDT
Structural
|
Annual
|
Manual
P 5.08-6.08
|
4.
|
Ali-Baba
Aka/1001
Nights
|
A. R.
M.
|
Check
main arm joint weldment, check main arm to center weldment, check car
mounting blocks and car frame weldments, check tower bolt blocks weldment,
check tower to trailer weldment, check car slewing ring mounting plate to arm
weldment
|
Non-destructive
test (NDT) must be completed every 2 years
|
Per
1001 Nacht’s or Ali-Baba Operations Manual, Section 6
|
|
5.
|
Ali-Baba,
aka 1001 Nights.
|
A.R.M
|
Welds
and Parent metal in their direct vicinity in all Critical Areas indicated by
drawing on P. 5.09 and described on P. 5.10 of the Manual (section 5).
|
NDT
to be performed annually, contact manufacturer for details.
General
Inspection to be
Performed
by 3rd Party
|
A.R.M
Ali-Baba Manual, section 5.
|
|
6.
|
High
Flyer/Screamer
|
A. R.
M.
|
NDT
Safety critical Areas
|
Annual
|
Manual
pgs. 5.07-6.01
|
|
7.
|
High
Flyer/Screamer
|
A. R.
M.
|
NDT
Safety critical Areas
|
Every
2 years
|
Manual
Pgs. 6.10-6.12
|
|
8.
|
Quasar
|
A. R.
M.
|
Lifting
Frames, weldment of main hinge boss to Link Assembly, and in the Link Parent
Metal
|
Annual
NDT (Electromagnetic and Ultrasonic recommended)
|
ARM
Bulletin S.B/QUA/03/003, dated February 1994
|
|
9.
|
Quasar
|
A. R.
M.
|
NDT
main lifting frame
|
Annual
|
SB
/QUA/03/003
|
|
10.
|
Sky
Master aka Tomahawk
|
A. R.
M.
|
NDT
structural
|
Every
2 years
|
Manual
P 5.19-5.21
|
|
11.
|
Sky
Master aka Tomahawk
|
A. R.
M.
|
Refer
to your owner's manual, page 5.10
|
Non-destructive
test (NDT) must be completed every 9 months
|
Per
ARM owner's manual, pages 5.06, 5.08, 5.09, and 5.10.
|
|
12.
|
Sky
Master aka Tomahawk
|
A. R.
M.
|
Over
the Shoulder Restraints
|
Replace
all over the Shoulder Restraints on your ride before the ride turns 5 year
old
|
Per
ARM US Bulletin SB 013007 dated 2/16/07 and Massachusetts Notice of
Recommended Action Dated 8/10/06
|
|
13.
|
Touchdown
6 Car
|
A. R.
M.
|
Diagrams
5.1 and 5.2
|
Non-destructive
test (NDT) must be completed annually
|
Per
ARM Operation & Maintenance Manual, Section 5
|
|
14.
|
Aerial
Trams & Lifts
|
All
|
Refer
to ANSI
|
Refer
to ANSI
|
Comply
with ANSI 4.34.3B77.1-1982 pertaining to testing of grips or clips
|
|
15.
|
Sky
Fighter
|
Allen
Herschell
|
Stabilizing
rods, threads
|
Non-destructive
test (NDT) must be completed annually
|
Per
U.S. Consumer Product Safety Commission safety notice dated June 9, 1992 and
August 2, 2000
|
|
16.
|
Coaster
(steel)
|
Arrow
|
Track
rails, strong back and ties, Saddle welds to strong back, Column welds
|
Non-destructive
test (NDT) must be completed annually or every 2000 hours
|
Per
Arrow technical bulletin #99-1 dated November 24, 1999
|
|
17.
|
Coasters
Corkscrew,
Loop and Suspended
|
Arrow-Huss
|
Welded
areas of track, anti-roll back units, chain guide wheel spindles, axle
housings, wheel carrier weldments, chassis main vertical spindle, body
support frame, hitch yoke
|
Non-destructive
test (NDT) must be completed annually
|
Per
Arrow-Huss bulletin dated November 17, 1981 and January 4, 1988 and the
operators Manual
|
|
18.
|
Coaster
|
Bolliner
& Mallard
|
3-10-09
Margaret will send in documentation from Manufacturer
|
|
|
|
19.
|
Coaster
Top
Gun
|
Bolliger
& Mallard
|
Per the
manufacturer’s requirements
|
Non-destructive
test (NDT) must be completed annually
|
Comply
with manufacturers maintenance manual and letter dated December 6, 2000
|
|
20.
|
Ski
Lift
Grips
Borvig
|
Borvig
|
Grips
|
Non-destructive
test (NDT) must be completed annually
|
Per
Borvig instruction manual & drawing. C-3064
|
|
21.
|
Balloon
Races
|
Bradley
& Kaye
|
Superstructure,
sweep support rod
|
Non-destructive
test (NDT) must be completed annually
|
Per
Balloon Races operations manual 1A thru 4
|
|
22.
|
Century
Wheel
|
Chance
|
Weld
between the main steel tube and the hub plate at the bottom of each gondola
(after removing access cover)
|
Annual
visual Non-Destructive Test
|
Per
Chance bulletin number 406CRM135-0 dated 03-31-05
|
|
23.
|
Trabant
|
Chance
|
Boom
|
Monthly
|
Per
Chance service bulletin #92
|
|
24.
|
Inverter
and
Double
Inverter
|
Chance
Manufacturing
|
Vehicle
arm, counterweight arm, vehicle arm, adapter box
|
Non-destructive
test (NDT) no longer required after May 6, 2003 - only visual inspection
required
|
Per
Chance 2001 field inspection guide, page 64 and page 66
|
|
25.
|
Falling
Star
|
Chance
Rides
|
Drive
sprocket
|
Non-destructive
test (NDT) must be completed annually
|
Per
Chance Rides bulletin #B391R11440 dated January 7, 1994
|
|
26.
|
Falling Star
|
Chance Rides
|
2 Vehicle Axles (Front & Rear)
|
1. Calculation of Axle’s accumulated number of revolutions before
Nov 3, 2009. 2. Axles that operated through 3 million revolutions or more
must be replaced or kept only if they pass annual NDT. 4. Axles that pass NDT
may be operated no more that 1 year thereafter, provided they pass annual NDT.
|
Chance Bulletin number
B391CRM166-0, dated October 3, 2009.
|
|
27.
|
Giant
Gondola Wheel
|
Chance
Rides
|
Torque
tube flange
|
Non-destructive
test (NDT) must be completed annually
|
Per
Chance Rides bulletin #B400R11750 dated May 17, 1996
|
|
28.
|
Sky
Wheel
|
Chance
Rides
|
Bull
wheel axle, boom axle
|
Non-destructive
test (NDT) must be completed annually
|
Per
Chance Rides bulletin #111 and Chance Rides bulletin #B379R1041-0 dated July
17, 1989
|
|
29.
|
Trabant
Casino
|
Chance
Rides
|
Per
the manufacturer’s bulletin
|
Non-destructive
test (NDT) must be completed annually
|
Per
Chance Rides bulletin #92 dated December 5, 1974
|
|
30.
|
Yo Yo
|
Chance
Rides
|
Sweep
lift cylinder (must be removed and sent to Chance for recertification)
|
Rebuild
and recertification Non-destructive test (NDT) must be completed every 5
years
|
Per
Chance Rides 1999 Field Inspection Test Guide, page 28 and bulletin
B376R1077-0
|
|
31.
|
Yo Yo
|
Chance
Rides
|
Sweep
Lift Cylinder Bearing Assembly
|
Uncover
assembly and insert ¼” gauge between upper bearing nut and gauge plate,
|
CRM
Bulletin B376CRM146-B, Dated Sept 4, 2008
|
|
32.
|
Zipper
|
Chance
Rides
|
Boom
weld at spindle
|
Non-destructive
test (NDT) must be completed annually on all units without the Chance Rides
Zipper repair kit.
|
Per
Chance Rides 1999 Field Inspection and Test Guide, Zipper, page 40 & 41
bulletins B106R1057-0 and A106R1057-A dated May 22, 1990
|
|
33.
|
Coaster
|
D.H.
Morgan Manufacturing
|
Axle
|
Annually,
as specified in manufactures manual
|
Per
D.H. Morgan Manufacturing letters dated March 7, 1988 and June 22, 1994
|
|
34.
|
Cliff
Hanger
|
Dartron
Industries
|
Car
hanger stem, all stem gusset joints
|
Non-destructive
test (NDT) must be completed annually on all rides built prior to January 23,
2004
|
Per
Dartron Industries safety bulletin # SR-5K-002 dated January 23, 2004
|
|
35.
|
Big
Eli Hy-5,
Eagle
16 and
Double
Eagle Wheels
|
Eli
Bridge Manufacturing
|
Drive-rim
removable bolts and pivot bolts.
|
Ultra
sound or X-ray. In addition to NDT requirements, gives wear limits of parts
(prompting replacement thereof), torque requirements for bolts, as well as
other requirements.
|
Per
Eli Bridge Manufacturing memo to all owners dated October 7, 2005.
Per
Patty Sullivan/Eli Bridge, this is a one-time requirement that Eli Bridge
will send out new bulletin to clarify.
|
|
36.
|
Monster
|
Eyerly
Aircraft Company
|
All
areas around structural modification, kit components, seat tubing
|
Non-destructive
test (NDT) must be completed annually
Non-destructive
test (NDT) must be completed every 5 Years
|
Per
Eyerly Aircraft Company notice dated June 12, 1981
U. S.
Consumer Product Safety Council safety alert dated September 13, 1994.
|
|
37.
|
Octopus
|
Eyerly
Aircraft Company
|
Eccentric,
sweep support rods, seat tubing
|
Non-destructive
test (NDT) must be completed annually
Non-destructive
test (NDT) must be completed every 5 Years
|
Per
Eyerly Aircraft Company, bulletins #0-48-86 and #0-50-86 --Per US Consumer
Product Safety Council bulletin dated August 16, 1994 & September 13,
1994.
|
|
38.
|
Spider
|
Eyerly
Aircraft Company
|
Eccentric,
sweeps w/16" base, sweep support rods, seat tubing
|
Non-destructive
test (NDT) must be completed annually
Non-destructive
test (NDT) must be completed every 5 years
|
Per Eyerly Aircraft Company, bulletins #0-48-86,
#0-49-86, #0-50-86 and #8-88-1 --Per US Consumer Product Safety Council
bulletin dated August 16, 1994 and September 13, 1994.
|
|
39.
|
Double Shock
|
Far Fabbri
|
Vehicle attachment bolts
|
Replace Bolts every 3 years, or Annual NDT (contact Fabri for type
of NDT), replace bolts failing NDT.
|
Operation & Maintenance Manual and per Fabbri Letter Dtaed
May1, 2008
|
|
40.
|
Raft
Ride
|
Fabbri
|
Centre
wheel shaft retaining socket to base frame welds
|
Annual
Visual Inspection. For possible additional NDT contact Fabbri
|
NAFLIC
Bulletin 350, Dated Aug 2008
|
|
41.
|
Crazy
Dance
|
Far
Fabbri
|
Sweep
hooks & welding
|
Non-destructive
test (NDT) must be completed annually (only applies to 1990–1995 models)
|
Per
Far Fabbri bulletin #FC 002
|
|
42.
|
Hi
Flyer
|
Far
Fabbri
|
Secondary
sweep ends
|
Non-destructive
test (NDT) must be completed annually
|
Per
Far Fabbri Bulletin #FR-034 magnetic particle inspection is NOT acceptable,
per Preston Amusement letter of April 20, 1994
|
|
43.
|
Kamikaze
(aka Ranger,
Hi
Flyer or Phoenix)
|
Far
Fabbri
|
Vehicle,
tower &counterweight bolts
|
Non-destructive
test (NDT) must be completed annually
|
Per
Far Fabbri bulletin #FR-034 magnetic particle inspection is NOT acceptable,
per Preston Amusement letter dated April 20, 1994.
|
|
44.
|
Phoenix
|
Far
Fabbri
|
Vehicle,
column & tower bolts
|
Non-destructive
test (NDT) must be completed annually
|
Far
Fabbri bulletin #FR-034 magnetic particle inspection is NOT acceptable, per
Preston Amusement letter dated April 20, 1994.
|
|
45.
|
Ranger
|
Far
Fabbri
|
Vehicle,
column and tower, bolts
|
Non-destructive
test (NDT) must be completed annually
|
Per
Far Fabbri bulletin #FR-034 -magnetic particle inspection is NOT acceptable
per Preston Amusement bulletin dated April 20, 1994.
|
|
46.
|
Sling
Shot
|
Funtimes
(Hnadeks Gesmbh
|
Swivel
shaft and capule welds - refer to operators manual
|
Per
operators manual every year. Paint must be removed every 5 years and weld
inspection be completed.
|
Per
Operators Manual
|
|
47.
|
Merry
Mixer
(Ground
Mount rides only)
|
Garbrick
Manufacturing
|
Seat
spindles
|
Non-destructive
test (NDT) must be completed annually for all GROUND mounted Merry Mixers.
Trailer mounted rides do not require NDT.
|
Per
manufacturer’s safety alert letter to all Merry Mixer ride owners dated July
3, 1991
|
48.
|
360 Degree (aka Typhoon)
|
General Kiddie Ride
|
Main
axle & axle housing, welded on shoulder supports, welded areas of legs,
welded areas of counterweight, revision of the gear teeth that support the
shoulder harnesses
|
A
Magnetic Particle and Dye Penetrant non-destructive test (NDT) must be
completed annually
A
visual non-destructive test (NDT) must be completed every 3 months
|
(ASTM),
F-24 Committee Standards on Amusement Rides and Devices
Per
Manufacturer, General Kiddie Rides letter dated March 21, 1991
|
49.
|
70
Degree (aka
Pirate
Ship or
Viking
Ship)
|
General Kiddie Ride
|
Main
axle & axle housing, welded areas of legs, change of security belts
|
A
Magnetic Particle, Dye Penetrant and X-ray non-destructive test (NDT) must be
completed annually
A
non-destructive test (NDT) must be completed annually
|
(ASTM),
F-24 Committee Standards on Amusement Rides and Devices
Per
Manufacturer, General Kiddie Rides letter dated March 21, 1991
|
|
50.
|
Pirate
Ship (aka
70
Degrees or
Viking
Ship)
|
General
Kiddie Rides
|
Main
axle, axle housing, weld area of legs
|
A
visual non-destructive test (NDT) must be completed annually
Magnetic
particle, Dye Penetrant and X-ray must be complete every 3 years
|
(ASTM),
F-24 Committee Standards on Amusement Rides and Devices
Per
Manufacturer, General Kiddie Rides letter dated March 21, 1991
|
|
51.
|
Typhoon
(aka
360
Degrees)
|
General
Kiddie Rides
|
Main
axle and axle housings, welded on shoulder supports, welded areas of legs,
revision of the gear teeth that support the shoulder harnesses, change of
security belts, welded areas of counterweight
|
Non-destructive
test (NDT) must be completed annually
A
visual inspection is required every 3 months
|
(ASTM),
F-24 Committee Standards on Amusement Rides and Devices
Per
Manufacturer, General Kiddie Rides
|
|
52.
|
Viking
Ship (aka Pirate Ship or 360 Degrees)
|
General
Kiddie Rides
|
Main
axle and axle housings, Welded areas of legs
|
Non-destructive
test (NDT) must be completed annually
|
(ASTM),
F-24 Committee Standards on Amusement Rides and Devices
Per
Manufacturer, General Kiddie Rides
|
|
53.
|
Steel
Coaster cars
|
Gerstlauer
|
Per
the manufacturer’s requirements
|
Non-destructive
test (NDT) must be completed annually
|
Comply
with manufacturers requirements
|
|
54.
|
Ejection
Seat
Permanent
120’
|
Gravity
Works
|
Towers’
leg to flange welds (about 40’ up from ground)
|
Magnetic
particle, annually, plus complete owner inspection of towers every 2000
launches
|
Per
Gravity Works letter to Ejection Seat owners, dated circa July, 2000
|
|
55.
|
Hustler
and
Tempest
|
Grover
Watkins
|
Per
the manufacturer’s requirements
|
Non-destructive
test (NDT) must be completed annually
|
Comply
with manufacturer’s safety bulletin dated August 24, 1978 & CPSC safety
bulletin
|
|
56.
|
Swinger
|
Grover
Watkins
|
Per
bulletin
|
Non-destructive
test (NDT) must be completed annually
|
Comply
with CPSC bulletin dated June 21, 1996
|
|
57.
|
Rock
Spin & Roll
|
Hampton
|
Tub
shafts
|
Non-destructive
test (NDT) must be completed annually
|
Per
Hampton bulletin #107-91
|
|
58.
|
Tubs
of Fun
|
Hampton
|
Main
shaft w/3" diameter tub shaft
|
Non-destructive
test (NDT) must be completed annually on rides made before January 1, 1979.
|
Per
Hampton Rides Bulletin #104-90, and Hampton Rides Bulletin #3105-90 which is
an addendum to #104-90 and #105-90
|
|
59.
|
All Rides
|
Hi – Lite
|
As required
|
Complete overhaul every 10 years
|
Ride Manuals
|
|
60.
|
Paratrooper
|
Hrubetz/
Kilinski, Man Co, Dartron
|
Spindle,
main spindle hub housing
|
Non-destructive
test (NDT) must be completed annually
|
Per
Man Co Manufacturing Company bulletin #QC-UI-I, Rev. 3; Bulletin #QC-MI-1-Rev
O; and bulletins BU-136MC and BU-138MC
Per
Dartron bulletin #BU 201 PR 01 dated January 15, 2002
|
|
61.
|
Enterprise
|
Huss
|
Bearing
block holders, car structure parts of the roof and parts above, at and below
pivot pins; and for cracks in the welds of these parts and welds that attach
these parts.
|
Non-destructive
test (NDT) must be completed annually
|
Per
U.S. Consumer Product Safety Commission - Enterprise Ride Interim Corrective
Action Plan dated December 7, 1993.
|
|
62.
|
Rainbow
|
Huss
|
Bevel
gears
|
Non-destructive
test (NDT) must be completed after every 5,000 hours of operation
|
Per
Huss recommended checking procedure dated January 5, 1990
|
|
63.
|
Super
Twist
|
King
|
Per
the manufacturer’s requirements
|
Non-destructive
test (NDT) must be completed annually
|
Per
the manufacturer’s requirements
|
|
64.
|
Swinger
|
King
|
Per
the manufacturer’s requirements
|
Non-destructive
test (NDT) must be completed annually
|
Per
the manufacturer’s requirements letter dated August 10, 1989
|
|
65.
|
After
Burner
|
KMG
|
Swing
arm weld of 12 sided tube to bottom bearing flange
|
One
time magnetic particle test of welds. Required corrective action is to repair
any cracked welds, and to install gussets to preclude future cracking.
|
Per
KMG bulletin number FRBSB006, dated August 8, 2007, impacting ride serial
numbers FRB-24-XX
|
|
66.
|
Freak
Out
|
KMG
|
Annual
Visual Inspection
|
Annual
|
Manual
Pg 10
|
|
67.
|
Super
Loop,
aka
Ring of Fire
|
Larson
International
|
Hinge
pins on units
|
Non-destructive
test (NDT) must be completed every 5 years
|
Per
Larson International service bulletin #94-1 dated July 18, 1994
|
|
68.
|
Caterpillar
(Raupenbahn)
|
Mack
|
Center
plate, sweeps, sweep bolts, holder for cover, gondola support frames, gondola
support bolts, gondola frames, safety bars, track, supports, base structure,
center decoration, center structure
|
Non-destructive
test (NDT) must be completed every 10 years or after 20,000 hours-some parts
Non-destructive
test (NDT) must be completed every 5 years or after 10,000 hours-some parts
Monthly
visual and dye penetrant, if crack is suspected
|
Per
NDT Guidelines for MACK Caterpillar” (Raupenbahn)
|
|
69.
|
Cortina
Bob
|
Mack
|
Safety
bars, gondola supports, track, supports, base, center decoration, center
structure
|
Non-destructive
test (NDT) must be completed every 5 years or after 10,000 hours and monthly
visual. If cracks are suspected non-destructive test/dye penetrant must be
completed annually
|
Per
Cortina Bob Operator’s Manual
|
|
70.
|
Himalaya
|
Mack
|
Center
plate, sweep bolts, sweeps, gondola bolts, gondola frames, safety bars,
gondola supports, track, supports, base, center decoration, center structure
|
Non-destructive
test (NDT) must be completed every 10 years or after 20,000 hours/some parts
Non-destructive
test (NDT) must be completed every 5 years or after 10,000 hours/some parts
Monthly
visual and if cracks are suspected a non-destructive test/dye penetrant must
be performed annually
|
Per
Mack Operator’s Manual
|
71.
|
Matterhorn
|
Mack
|
Refer
to test guidelines
|
Refer
to test guidelines
|
Comply with the manufacturer’s test guidelines and
letter dated January, 2000
|
72.
|
Music
Express
|
Mack
|
Center
plate, sweep bolts, sweeps, gondola supports, gondola bolts, gondola frames,
safety bars
|
Non-destructive
test (NDT) must be completed every 10 years or after 20,000 hours
Non-destructive
test (NDT) must be completed every 5 years or after 10,000 hours
|
Per
Music Express Operator’s Manual
|
73.
|
Round
Up
|
Man Co
Manufacturing
|
Main
boom rocker shaft, cylinder anchor shaft, spindle, main spindle hub housing
|
Semi-Annually
as follows: For Round-Up rides operating in Illinois on or between April 1
and Oct. 31; the NDT must be performed after March 22 and before operation.
For Round-Up rides operating in Illinois on or between Nov. 1 and March 31;
the NDT must be performed after Oct. 22 and before operation.
|
Per
Man-Co Manufacturing bulletin CO QC-UI-I, Rev. 3: QC-MI-1-Rev O; and
bulletins BU-136MC and BU-138MC, and Dartron bulletin BU0201 PR01, dated
January 15, 2000
Unless
at the time of the NDT inspection, the Department places a seal upon the ride
prohibiting the assembly and operation until the Department removes that
seal.
|
|
74.
|
Fireball
|
Man Co
Manufacturing Company
|
Spindle,
main spindle hub housing
|
Non-destructive
test (NDT) must be completed annually
|
Man
Co Manufacturing Company
#QC
UI-I; Rev. 3: #QC-MI-1, Rev. O; and bulletins #BU-136MC and #BU-138MC
|
|
75.
|
Matterhorn
|
Matterhorn/Petersburger
Schlittenfahrt
|
Sweep
slew rings, sweep bolts, sweeps, wheel axles, gondola, bearing pins,
intermediate, rods, gondola frames, safety bars
|
As
specified in the Matterhorn/Petersburger Schlittenfahrt’s operator’s manual
|
As
specified in the Matterhorn/Petersburger Schlittenfahrt’s operator’s manual
|
76.
|
Coaster,
kiddie
|
Miler
(only applies to coasters built after 1991)
|
Truck
& structure, car bodies & frames, wheels & axles, hitch assy.,
lap-bar assy.
|
Non-destructive
test (NDT) must be completed annually on all coasters built after 1991
|
Per
Miler Coaster Operation Manual, pages 15-17
|
|
77.
|
Wood
Coaster Vehicles
|
Morgan
|
Per
the manufacturer’s requirements
|
|
Comply
with the manufacturer’s requirements per letters dated March 7, 1988 and June
22, 1994
|
|
78.
|
Coaster,
full size
|
Philadelphia
Toboggan Company
|
Tractor
wheel frame, axle, friction wheel frame, square head axle, clutch axle,
clutch, coupler pin, draw head front, draw head rear
|
Non-destructive
test (NDT) must be completed annually
|
Per
Philadelphia Toboggan Company bulletins dated April 22, 1988 and December 10,
1992
|
|
79.
|
Coaster,
Junior Size
|
Philadelphia
Toboggan Company
|
Rear
coupler, front coupler, frame, spindle, spindle frame
|
Non-destructive
test (NDT) must be completed every 2 years
|
Per
Philadelphia Toboggan Company bulletin dated April 22, 1988
|
80.
|
Explorer
aka
Matterhorn
|
Revershon
|
Capsule
support axle
|
Non-destructive
test (NDT) must be completed semi-annually or every 1000 hours
|
Per
Revershon’s owner’s manual
|
|
81.
|
Frog
Hopper and Rodeo Rider
|
S
& S Power, Inc.
|
Boom
and base welds (refer to bulletin) every three (3) years
As
shown on bulletin
|
Non-destructive
test (NDT) must be completed annually
MT/PT
every 3 years
|
Per S
& S Power, Inc. bulletin # 03.10.10 dated October 9, 2003
S
& S Drawing Numbers F-FRG-BOO-W-@, 002125, and 002278 on Frog Hopper/Rodeo
Rider
|
|
82.
|
Turbo
Force
aka
Stratoshere
|
Soriani
|
Tie
rods
|
Non-destructive
test (NDT) must be completed annually on rides made before 2004 with specific
serial numbers
|
Per
Soriani bulletin #2004 TF02 dated September 14, 2004
|
|
83.
|
Super
Loop on top (Crazy Flip)
|
Soriani
& Moser
|
Gondola
arms joint
|
Non-destructive
test (NDT) must be completed annually
|
Per
Soriani & Moser Logbook pages 53, 54
|
|
84.
|
Orbiter
(Predator)
|
Tivoli
|
Car
attachment pins
|
Non-destructive
test (NDT) must be completed annually
|
Per
Tivoli bulletin #00120 dated December 10, 1990
|
|
85.
|
Predator
(Orbiter)
|
Tivoli
|
Car
attachment pins
|
Non-destructive
test (NDT) must be completed annually
|
Per
Tivoli bulletin #00120 dated December 10, 1990
|
|
86.
|
Scorpion
|
Tivoli
|
Pivot
balls, main sweep flange bolts
|
Non-destructive
test (NDT) must be completed every 2 years
|
Per
Tivoli bulletin #001 for the Scorpion Ride
|
|
87.
|
Spin
Out aka
The
Claw, Maelstrom, El Nino
|
Tivoli
|
Refer
to bulletin
|
Non-destructive
test (NDT) must be completed annually
|
Per
Tivoli bulletin #SOSA0001-SOSA13 and U.S. Consumer Product Safety Commission
safety alert dated March 30, 2004
|
|
88.
|
Star
Force
|
Tivoli
|
Vehicle
frame, car pivot ball, vehicle sweeps, sweep spreader, main sweep arms
|
Non-destructive
test (NDT) must be completed annually
|
Per
U.S. Consumer Product Safety Commission safety alert dated September 13, 1994
|
|
89.
|
Corkscrew,
MK
1200, MK-900 and Suspended Looping Coasters
|
Vekoma
|
Main
axle, wheel spindles, guide sheels, up stop wheels, coupling, anti-roll
backs, chassis
|
Non-destructive
test (NDT) must be completed annually
|
Per
Velcoma Coaster Technical bulletins #V90-3 and #V90-4
|
|
90.
|
Suspended Looping
Coaster
|
Vekoma
|
Suspended Seats
|
Welds marked in blue in the Suspended Seat Drawing in Bulletin are
to be tested by MT, whereas welds marked in red sre to be tested by UT.
Please contact Manufacturer regarding frequency of testing.
|
Vekoma Bulletin No. 1-SB-006-
14052009, dated May 20, 2009.
|
|
91.
|
All
Rides
|
Venture
|
All
Components
|
10
yrs Overhaul
|
Required
by the Manual
|
|
92.
|
Go
Rounds
|
Venture
|
Critical
components
|
Non-destructive
test (NDT) must be completed every 16,000 hours or after 10 years
|
Per
Venture-Go-Round operators manual
|
|
93.
|
Parachute
Tower
|
Venture
|
Cylinder
path, cylinder clevis, elevator head, tower base plate, 12” sheave shafts,
attachments--turn buckle
|
Non-destructive
test (NDT) must be completed every 5 Years
|
Per
Venture manual, Section 3.1.5.3
|
|
94.
|
Hustler
|
Watkins
|
Secondary
sweep shafts, car center pins
|
Non-destructive
test (NDT) must be completed annually
|
Per the IL
Carnival-Amusement Safety Board –Refer to Grover C. Watkins Inc., Emergency
Safety Bulletin for Tempest dated August 24, 1978.
Per
the U.S. Consumer Product Commission Safety bulletin dated August 4, 1993
(car center pins)
|
|
95.
|
Swinger
|
Watkins
|
Upright
tube
|
Visual
at every set up, if cracks are observed non-destructive test (NDT) must be
completed annually
|
Per
U.S. Consumer Product Safety Commission safety alert dated June 21, 1996
|
|
96.
|
Tempest
|
Watkins
|
Secondary
sweep shafts, car center pins
|
Non-destructive
test (NDT) must be completed annually
|
Grover
C. Watkins Inc., emergency safety bulletin, dated August 24, 1978, and U.S.
Consumer Product Safety Commission Safety bulletin dated August 4, 1993.
|
|
97.
|
Adult
Coaster Cars
|
Wisdom
|
Inspection
of Wheel Bracket Assembly
|
Visual
& dye penetrant or magnetic flux
|
Per
Wisdom bulletin dated February 25, 2004. Drawing number 9C 025
|
|
98.
|
Family
Himalaya
|
Wisdom
|
NDT
Wheel shafts
|
Every
3 yrs
|
Manual
p.45
|
|
99.
|
Gravitron
|
Wisdom
|
Console
Post
|
Turn
Off Main Electrical Power, Lock Out the Disconnect, then visually inspect
welds and parent metal for cracks, as detailed in Bulletin
|
Part
of a Gravitron Bulletin Package dated Aug 12, 1993
|
|
100.
|
Himalaya
one
truck
|
Wisdom
|
Secondary
sweep ends
|
Non-destructive
test (NDT) must be completed annually unless sweep kit has been installed
|
Per
Wisdom service bulletins dated March 15, 2000, and November 12, 2000 and
clarified by V. Wisdom’s letter of January 31, 2001
|
|
101.
|
Himalaya
Silver Streak, Family
|
Wisdom
|
Sweeps
|
Non-destructive
test (NDT) must be completed annually unless sweep kit installed
|
Per
Wisdom service bulletin dated April 22, 2002
|
|
102.
|
Laser
Ship
|
Wisdom
|
Ears
and their weldments, see bulletin
|
Magnetic
Flux, Non-destructive test (NDT) must be completed annually (per Vic Wisdom
not clear in bulletin)
|
Per
Wisdom’s service bulletin dated November 1, 2005
|
|
103.
|
Magic
Carpet
|
Wisdom
|
Main
pivot shaft, seat pivot pin
|
Non-destructive
test (NDT) must be completed annually
|
Per
Wisdom’s inspection guide requirements, seat pivot pin Fabricated and Rebuilt
Rides, page 10, item 9
|
|
104.
|
Sizzler
|
Wisdom
|
Cabbage
head ears, main center pole shaft
|
Non-destructive
test (NDT) must be completed annually
|
Per Wisdom’s inspection guide, Fabricated &
Rebuilt Rides, page 2, item 11 and drawing 01-100 and bulletin dated June 3,
1985 and July 1994
|
|
105.
|
Twizzler
|
Wisdom
|
Car
frames, rod ball swivel ends, frame pivot bushing, drive rim
|
Non-destructive
test (NDT) must be completed annually visual
|
Per
Wisdom’s letter dated February 22, 2001 and the operators manual
|
|
106.
|
Crazy
Bus
|
Zamperla
|
Welds
on rotating hub flange
|
Non-destructive
test (NDT) must be completed annually (only applies to rides built from
1990-1995)
|
Per
Zamperla service bulletin #99CB1 dated June 28, 1999
|
|
107.
|
Crazy
Bus
|
Zamperla
|
Motor
Brake Liner
|
Quarterly
Visual Inspection (every 3 months)
|
Per
Zamperla Bulletin No: 08CB02, dated Nov 14, 2008
|
|
108.
|
Dragon
or
Tornado
Coaster
|
Zamperla
|
Vertical
spindles
|
Non-destructive test
(NDT) must be completed annually
|
Per
Zamperla maintenance bulletin dated January, 1991
|
|
109.
|
Enterprise,
Mini
|
Zamperla
|
Vertical
spindle
|
Non-destructive
test (NDT) must be completed annually only if cracks are suspected
|
Per
Zamperla maintenance bulletin dated January, 1991
|
|
110.
|
Lolli
Swing
|
Zamperla
|
Center
section (must check for reinforcements)
|
Weekly
visual
Non-destructive
test (NDT) must be completed annually on all units without factory
reinforcement
|
Per
Zamperla bulletin #97LS.1 dated March 20, 1998
|
|
111.
|
Mini
Enterprise
|
Zamperla
|
See
Zamperla bulletin number 2002 ME01, dated December 6, 2002 and attached
drawing
|
One
time Magnetic Particle testing of welds, different locations. ( See bulletin
drawing ) Monthly visual inspection of the welds thereafter.
|
Per
Zamperla bulletin number 2002 ME01, dated Dec. 6, 2002 and attached drawing,
plus Zamperla email dated 1/10/08.
|
|
112.
|
Samba
Balloon
|
Zamperla
|
Center
column base, center frame structure
|
Non-destructive
test (NDT) must be completed annually
For
rides manufactured after December 8, 1997, if Zamperla repair kit has been
installed, a non-destructive test (NDT) is not required
|
Per
Zamperla bulletin #97SB1 dated December 8, 1997
|
|
113.
|
Speedway
|
Zamperla
|
Support
bars
|
Non-destructive
test (NDT) must be completed annually
|
Per
Zamperla service bulletin #99-SW1 REV dated July 2, 1999
|
|
114.
|
Wave
Swinger
|
Zierer
|
Various
|
Numerous
(see chart for Test Method Code Legend). Frequency also varies. (see chart
for Time Code Legend).
|
Per
Zierer bulletin (no English bulletin number) dated March 28, 2005. Gives NDT
requirements, detailed wear limits on parts (prompting replacement thereof).
Plus maintenance instructions.
|
|
115.
|
Coaster
(ZL42)
|
Zyklon
Loop
|
Welded
structural joints, center plate, sweep bolts, sweeps, gondola bolts, gondola
frames
|
Non-destructive
test (NDT) must be completed after each 960 hrs of use
Non-destructive
test (NDT) must be completed every 10 years or after 20,000 hours
|
Per
Zyklon Loop Maintenance Manual, page 19
|